West Village, Detroit, MI — A turnkey, fixed-price custom home build crafted to your vision. This portal is your single source of truth for selections, timeline, payments, and answers.

Contract Price
$498,000
Lump Sum · Turnkey
Down Payment
20% Min.
$99,600 minimum
Build Timeline
6–8 Months
From permit approval
Warranty
1-Year
Workmanship coverage
CLIENT
Samantha Fisher
BUILDER
Sterling Construction
DESIGNER
Bo (Woodward Throwbacks)
LENDER
Lake Michigan Credit Union
CONTRACT TYPE
AIA Fixed-Price
LOAN OFFICER
Brad Woolman, NMLS #1064261

Phase-by-Phase Construction Plan

Estimated total duration: 6–8 months from permit approval. Detroit's permitting process adds a realistic buffer — Sterling is actively managing city relationships to minimize delays.

01

Pre-Construction & Permitting

● IN PROGRESS1–3 Months
  • AIA contract execution & 20% down payment
  • Architectural plan finalization with designer Bo
  • City of Detroit BSEED permit application submission
  • DWSD water tap permit (via licensed master plumber)
  • DPW right-of-way permit for utility connections
  • Plan review cycle — Zoning, Structural, Energy Code
  • Material selections finalized (spec book sign-off)
Detroit's permitting process is relationship-based and can take 6–8 weeks per cycle. Sterling is actively managing this timeline.
02

Horizontal Work (Draw 1)

○ UPCOMING4–6 Weeks
Draw 1 Payment Due
  • Site excavation and layout staking
  • Underground utility trenching (water, sewer, storm, electric, gas)
  • Footings and poured concrete foundation walls
  • Foundation waterproofing system
  • Drain tile system installation
  • Basement slab pour
  • Backfill and rough grading
  • Front porch flatwork and exterior concrete
Draw 1 payment is due at completion of all horizontal/underground work. This covers everything below grade and at grade.
03

Vertical Construction (Draw 2)

○ UPCOMING3–5 Months
Draw 2 Payment Due
  • Complete dimensional lumber framing package ($38,069 material budget)
  • Floor systems, exterior & interior walls, roof trusses
  • Roof sheathing, underlayment, GAF Timberline HDZ shingles
  • LP SmartSide engineered wood siding & trim
  • Energy-efficient windows (Andersen 400 Series)
  • Exterior doors, gutters, and downspouts
  • HVAC: furnace, A/C, ductwork, thermostat
  • Full plumbing rough-in and electrical rough-in
  • Insulation to Michigan energy code
  • Drywall installation, finish, and sanding
Draw 2 payment is due at completion of all vertical construction (framing through drywall). Interior finish work follows.
04

Interior Finishes & Completion

○ UPCOMING6–8 Weeks
  • Interior doors, trim, base, and casing (7¼" baseboard, 4¼" window/door casing)
  • Kitchen & bathroom cabinetry (Hampton Bay soft-close shaker)
  • Countertops per selections (quartz/granite/laminate by room)
  • Flooring installation (engineered hardwood, LVP, carpet, tile)
  • Interior painting per designer palette
  • Appliance installation (Samsung suite + washer/dryer)
  • Final plumbing and electrical trims
  • Hardware installation (Schlage locks, cabinet pulls)
  • Final cleaning and punch list
05

Certificate of Occupancy & Handover

○ UPCOMING1–2 Weeks
  • Final city inspections (BSEED)
  • Certificate of Occupancy issued
  • Final walkthrough with Samantha & designer Bo
  • Warranty documentation delivered
  • Keys and home manual handover

Two-Draw Construction Payment Plan

Sterling Construction uses a straightforward two-draw structure aligned with your Lake Michigan Credit Union construction draw mortgage. Payments are tied to verified construction milestones — no surprises.

Pre-Approved: 20% Down Conventional Construction Draw Mortgage
Lake Michigan Credit Union · Brad Woolman, NMLS #1064261 · (810) 691-9644 · [email protected] · Up to $500,000
PRE-APPROVED
D
$99,600
20% of contract · Minimum required
Due at contract signing. Confirms project commitment and initiates the pre-construction and permitting phase. Aligns with your LMCU 20% down construction mortgage.
TRIGGER
AIA Contract Execution
1
$199,200
50% of balance · ~40% of total
Due upon completion of all horizontal and underground work. Covers everything at or below grade.
Excavation & site work
Underground utilities (water, sewer, storm, electric, gas)
Foundation footings & poured concrete walls
Foundation waterproofing
Drain tile system
Basement slab
Rough grading & exterior flatwork
TRIGGER
Foundation & underground complete — verified by inspector
2
$199,200
50% of balance · ~40% of total
Due upon completion of all vertical construction through drywall. Covers everything above grade through interior rough-in.
Complete framing package ($38,069 lumber budget)
Roofing system (GAF Timberline HDZ)
LP SmartSide siding & exterior doors
Windows (Andersen 400 Series)
HVAC, plumbing & electrical rough-in
Insulation to Michigan energy code
Drywall installation & finish
TRIGGER
Framing through drywall complete — verified by inspector

Payment Summary

PAYMENTMILESTONEAMOUNT% OF CONTRACT
Down PaymentContract signing$99,60020%
Draw 1 — HorizontalUnderground & foundation complete$199,20040%
Draw 2 — VerticalFraming through drywall complete$199,20040%
TOTAL$498,000100%

* This is a fixed-price, lump-sum contract. No change orders will be issued unless Samantha requests upgrades beyond the agreed specifications. All draws are subject to lender inspection and approval per LMCU construction draw mortgage terms.

Your Mid-Grade Specification Package

All selections below reflect the mid-grade package included in the $498,000 lump-sum contract. These are the products Sterling Construction will source and install. Samantha's design boards (created with designer Bo of Woodward Throwbacks) have been incorporated throughout.

Soft-Close Cabinets Confirmed

As discussed, all kitchen and bathroom cabinetry will include soft-close hinges and drawer glides. This is a mid-grade standard, not an upgrade.

Material selections sample board
🍳

Kitchen

SAMANTHA'S SELECTION BOARD
Kitchen selection board
Cabinets

Hampton Bay Franklin — Gray/Greige, Soft-Close, Shaker Style

View
Cabinet Color

Gray, Greige, or Sage Green (Samantha's preference)

Hardware

Black/Silver/Brushed Nickel — Bar pulls or cup pulls

Countertops

Granite or Quartz — MSI Q Premium or Formica Laminate (Patine Concrete 3706 / Argento Romano 6697)

View
Kitchen Island

Wood butcher block top (open + stone shelves below) — Dad is making ×3 pendants above

Sink

Costco undermount workstation sink with pot filler

Appliances

Samsung — Range, Refrigerator (French Door), Dishwasher, Over-Range Microwave (Stainless/Black Stainless)

View
Range Hood

Wall-mount chimney hood — Stainless or Black

Backsplash

Tile backsplash with floating shelves in front of window

City of Detroit — Plan Review Comments

These are the open comments from Detroit BSEED's Cycle 1 plan review (December 2025). Sterling's team is actively working through each item. All items are being addressed in the resubmittal package.

9 OPEN ITEMS — CYCLE 1
BSEED · 1780 Townsend St, Detroit, MI

Key City Contacts

Peter Young
BSEED Development Resource Team
[email protected] · (313) 518-1175
General questions & concerns
Christine Dalton
BSEED Customer Service — Building Permits
[email protected] · (313) 224-3233
Building permit guidance at DRC
Austin Johnson
DWSD Engineer
Detroit Water & Sewerage Dept.
Water tap permits, sewer easement (10-ft clearance required), GSI credits

Frequently Asked Questions

Every question raised during the Phase 3 proposal review — and more — answered clearly and completely. If something isn't covered here, contact Sterling directly.

Ready to Move Forward?

Your next step is the Friday 10:00 AM follow-up call with Sterling Construction. Review this dashboard with designer Bo beforehand, and come prepared with any remaining questions.

Rick McKiddy — Director of Estimating
Sterling Construction · AIA Fixed-Price Contract